Reconstruction of Municipal road to s.Mojanci
Investor: Municipality of Kochani. Contract value: 15.187.000denars. Length of the road: 3.000km. Paved surface: 14.000m2. Installed curbs: 6.000km. Construction of pavement: 2.500m2.

Reconstruction of road to Monastery St. Joakim Osogovski - Kriva Palanka
Investor: Center for development of the Third North-East planning region - Kumanovo. Contract value: 15.928.000denars. Time of construction: February - May 2020. Length of the road: 2,7km. Paved surface:

Reconstruction of local road to s.Strmosh - Municipality of Probishtip
Investor: Municipality of Probishtip. Contract value: 10.561.000denars. Time of construction: March - August 2020. Length of the road: 1,8km. Paved surface: 16.000m2. Excavation: 1.500m3. Buffer layer: 2.000m3.

Connection of Kochani with Orizari Phase 1
Investor: Municipality of Kochani. Contract value: 6.956.975,00 denars. Time of construction: year 2019.

Construction of Lazar Stoimenov Street in Orizari - Kochani
Investor: Municipality of Kochani. Contract value: 6.054.656,80 denars without VAT. Time of construction: year 2019. Features: Lenght: 718m, Excavation: 2.820m3. Buffer layer: 1.800

Construction of a trade and business facility in n. Babi - Shtip
Investor: KIT - GO Shtip. Contract value: 5.806.410,00 den. Time of construction: year 2019. Features: Excavation: 9.130m3. Hard concrete: 780m3. Built-in reinforcement:

Construction of Tailings Pond no. 4 in Mine Sasa
Investor: Mine SASA - Subcontractors to: STRABAG AG - Skopje Branch. Contract value: 45.000.000,00 denars with VAT. Time of construction: year 2017/2018. Features: Machine excavation: 53.120

Construction of a multi-story garage on st. JNA Boulevard in Shtip
Investor: KIT - GO Shtip. Contract value: 10.495.088,00 den without VAT. Time of construction: year 2017. Features: Excavation: 7.380m3. Hard concrete: 2.200m3. Built-in

Construction of street Industriska in M.Kamenica
Investor: Municipality of Makedonska Kamenica. Contract value: 13.500.000,00denars with VAT. Time of construction: year 2016. Features: Lenght: 420m, Excavation: 1.420m3. Buffer layer: 800