Construction of Tailings Pond no. 4 in Mine Sasa

Investor: Mine SASA - Subcontractors to: STRABAG AG - Skopje Branch
Contract value: 45.000.000,00 denars with VAT.
Time of construction: year 2017/2018.

Features:

Mechanical excavation: 53.120 m3.
Machine excavation by blasting: 20.600 m3.
Machine excavation with transport: 49.100 m3.
Making of embankments: 25.324 m3.
Excavation of improved material and construction of a dam embankment by compaction in layers: 46.000 m3.